Skip to main content

Completing or Deleting study does not cancel Planned or In-Progress Tasks

Written by Gemma
Updated over 5 months ago

Issue:

When a study is marked as Completed or Deleted, tasks which are In Progress or Planned status are not cancelled. They may show up on the Batch Maintenance screen.

Workaround:

Cancel all In Progress compliance events before marking a study Completed or Deleted.

Resolution:

This bug is being tracked as ADO-113438 and will be resolved in a future release.

Found in Version: 2.23.4

Fixed in Version: TBD