Skip to main content

Reassigning an In-Progress task (where there are multiple task assignees) will cancel the other tasks

Written by Gemma
Updated over 5 months ago

Issue:

When a task contains multiple assignees and is In Progress, if one of the individual tasks is reassigned, this action will cancel the other assigned tasks:

ss8.png

Workaround:

Instead, edit the parent task to reassign task assignees which will retain the other In Progress tasks:

ss9.png

Proposed Resolution:

ADO-59983 has been raised to track this issue.

Affects Version(s):

Release version 2.20 - 2.23.3.x

Fixed Version:

Disclose 2.23.4

Did this answer your question?